June 2012 Student Housing Construction Update

Student housing construction has ramped up at a fast pace as June came to a close. This included the completion of the lower and upper level parking garage foundations, as well as the storage and mechanical rooms, followed by starting the building infrastructure installation.

Lower level parking concrete work completed.

June 6: Lower level parking concrete work completed. Upper level parking column and wall support under construction.

 

Parking garage vertical support wall construction.

June 6: Parking garage vertical support wall construction.

 

Cement blown in to form "shotcrete" walls in parking garage.

June 6: Cement blown in to form "shotcrete" walls in parking garage.

 

Upper level parking deck framework underway.

June 6: Upper level parking deck framework underway.

 

View of site from northeast corner.

June 6: View of site from northeast corner.

 

Ramp to upper level parking deck rebar structure in place.

June 13: Ramp to upper level parking deck rebar structure in place. Lower level parking opening visible in center of photograph (see arrow).

 

View from corner of 7th and Shatto of building radius wall.

June 13: View from corner of 7th and Shatto of building radius wall.

 

Site overview.

June 13: Site overview.

 

View of site from southwest corner.

June 20: View of site from southwest corner.

 

Site overview.

June 20: Site overview.

 

View of site from northeast corner.

June 28: View of site from northeast corner.

 

Radius wall construction.

June 28: Radius wall construction.

 

View from Shatto Place of upper level parking area, storage and mechanical rooms.

June 28: View from Shatto Place of upper level parking area, storage and mechanical rooms.

 

Site overview.

June 28: Site overview.

 

Cement crane pouring upper level parking deck.

July 2: Cement crane pouring upper level parking deck.

 

Completion of upper level parking deck cement pour.

July 2: Completion of upper level parking deck cement pour.

 

Coming in July: Construction of the first floor, including cementing the first floor vertical radius walls along Seventh and Shatto.